Custom Bg

Construction Update — November 1



The finishing touches are in progress with a projected January opening date. Sheet rock, stucco, ceiling tiles, doors, and floors will be on the agenda for November; plumbing in December! Thanks for your patience and understanding throughout the construction project

Construction Update — October 1


We are under roof and the finishing trades begin taking over. Watch for solar panel installation, stucco work as well as sheet rock, ceiling, final HVAC work, and plumbing all begin to shape up the final product! Thanks for your understanding and cooperation throughout the construction process.

Construction Update — September 1




Construction Update — August 1




Framing is complete! As we move inside the new building, watch for the installation of HVAC units, electrical fixtures, fire sprinklers, roofing, windows, and more as we complete the guts of the new construction. Once again, thank you for your patience during the construction process.

Construction Update — July 1




The new Fitness Room framing is on schedule and is expected to be completed by July 31st. Please observe all signage regarding construction obstacles and watch for more updates

Construction Update — June 1


Men at Work


As you can see, construction is literally moving along very nicely now that we've brought in the big artillery; framing should be complete by the end of the month.

Interior trades such as plumbing, electrical, heating and air conditioning, as well as sprinkler system installations should be next on the schedule.

We'll continue to keep you informed of our progress.

Parking Lot Closures


With construction moving forward we will experience some periodic parking lot closures. These are done for the safety of ARFC's members.

When the parking lot is closed, it means that heavy equipment and or heavy materials are being moved around. This will be a periodic event throughout construction and we ask for you patience and cooperation during this project.

Construction Update — May 1



During the month of May construction activities will include continued framing of the new building in place of the rooftop tennis court. In the offices of the main hallway — Tennis Office, Healing Center, General Manager's Office, Accounting Office and Sales Office — walls will be open to secure/increase footing sizes to support additional weight of a second floor. Restrooms upstairs near babysitting will be converted to two ADA bathrooms.

Construction Update — April 1


We've finally obtained our building permit and began building in April. Our addition will include the conversion of the rooftop tennis court to a Small Group Training Room (leaving the downstairs gym to members for their own workouts); a larger Pilates/Barre Studio; and a 2500 square foot Group Exercise Studio.

This is phase 1 of the addition. Phase 2 will include the expansion of children's spaces for ARFC's Junior Members.